ENOVA, in partnership with the Dutch environmental consultancy TAUW, completed a contamination investigation supporting the European Bank for Reconstruction and Development’s planned investment in Kosovo’s electricity transmission network. The wider investment will modernise KOSTT substations and high-voltage infrastructure, improve energy security and support the integration of up to 300mw of new energy capacities, including renewables.
The investigation focused on potential environmental risks associated with transformer oils, polychlorinated biphenyls (PCBs) and other hazardous substances. PCBs are persistent organic pollutants formerly used in electrical equipment such as transformers and capacitors. They degrade slowly, can spread through soil, water and air, accumulate in the food chain and pose long-term risks to human health and the environment.
During a seven-day field campaign, the project team investigated 14 substations and 27 transformers across Kosovo. A total of 57 soil, 26 transformer oil and five groundwater samples were collected and analysed for PCBs, petroleum hydrocarbons, polycyclic aromatic hydrocarbons and selected heavy metals.
The assessment went beyond laboratory testing. Geological, hydrogeological and land-use data were reviewed, nearby wells and sensitive receptors were mapped, and Initial Conceptual Site Models (CSMs) were prepared to identify potential contamination sources, pathways and receptors.
A comprehensive transformer inventory was also developed, documenting the technical characteristics and PCB status of the investigated equipment. Using the internationally recognised CIRIA C552 framework, the team classified potential risks and prepared site-specific recommendations and a plan for further investigations where required.
By identifying potential environmental liabilities before rehabilitation works begin, the assignment supports safer project implementation, protects workers and the environment, and contributes to the development of a cleaner and more resilient electricity transmission network in Kosovo.